Roland Bunnik Bromelia´s, Pijnacker, Netherlands

Genset / gas engine: 2 x TCG 2020 V12
Segment / gas type: natural gas
Customer: Ronald Bunnik Bromelia’s - Pijnacker, Netherlands
Total output: 2,400 kWel
Commissioning: 2009

Since the beginning of 2009, the business has been using a CHP installed by MWM. Together with Ronald-Jan Post from DLV, Ronald Bunnik Bromelia’s decided to install a 2.4 megawatt power plant solution, divided in two 1.2-megawatt engines. 

 Delivery to the mains network has only been possible in Pijnacker since 1 January 2009. That is also the reason why a CHP was not purchased earlier.